Oral variation to written contract
Written contracts can be varied orally post-signature unless they specifically state to the contrary.
The case of MWB Business Exchange Centres v Rock Advertising illustrates the point.
A property landlord was found by the Court of Appeal to have wrongfully excluded a tenant who was in rent arrears, having earlier orally agreed to stay its hand.
The tenant, who was about £12,000 in arrears of licence fees and other charges, was locked out of its serviced offices by the landlord. The latter’s claim to payment of the arrears was upheld by a judge and the tenant’s counterclaim that it had been entitled to remain in occupation of the premises was rejected.
In upholding the tenant’s challenge to that decision, however, the Court found that an oral agreement by which the landlord accepted that payment of the arrears could be rescheduled and that the tenant could remain in occupation in the interim was binding on both parties.
The tenant successfully argued that there was nothing in the licence agreement which precluded its oral variation at a later date. Its agreement to pay £3,500 of the debt straight away, and to make arrangements for payment of the arrears in full over time, was sufficient consideration to make the oral variation enforceable.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
HSE prosecutes company for putting workers at risk
Roofing company fined and its director sentenced.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.